Phased Hotel Door Renovation: Replacing Doors Floor by Floor in an Occupied Building
Replacing doors while a hotel keeps trading is mostly a scheduling challenge. This guide explains how to phase survey, delivery and installation so guests notice as little as possible.
A phased hotel door renovation lets you replace room, bathroom and wardrobe doors while the property stays open, without taking whole wings out of sale. The door model matters less here than the programme: how many rooms are closed at once, how doors reach each floor, and how quickly each opening is made good. This guide walks through the planning steps we recommend to owners, operators and contractors.
Why phasing matters more than the door design
In a new build, doors are installed when the building is empty. In an occupied hotel, every hour of work competes with check-in, housekeeping and guest sleep. A well-chosen door that arrives at the wrong time or in the wrong sequence still creates complaints and lost room nights.
Treat the project as a logistics exercise first. Once the phasing logic is agreed, selecting the door model, finish and hardware becomes much simpler because the production batches follow the same logic.
Step 1: Survey before you order anything
Existing openings are rarely identical, even in the same corridor. A survey of every opening is the foundation of a floor by floor renovation, and it should be done before final door sizes are fixed.
- Measure clear opening width, height and wall thickness for each door.
- Record the existing frame type: timber, steel or concealed, and whether it will be kept or replaced.
- Note hand of opening, swing direction and floor finish, since undercuts depend on it.
- Photograph each opening and label it with the room number.
- Flag rooms with out-of-square frames, uneven floors or previous repairs.
If you plan to keep existing frames, the survey is even more important, because new leaves must be made to suit what is actually on site rather than what the old drawings show.
Step 2: Build a door schedule that follows the phasing
Organise the schedule by floor and room type, not only by door type. Each line should carry the room number, door function, size, hand, finish, hardware preparation and the phase in which it will be replaced. A schedule built this way lets the factory pack and label by phase, and lets the site team see exactly what belongs where.
Keep a small allowance for spare leaves. In renovation work, one or two openings per floor often turn out to need adjustment, and a spare saves a room being out of order for weeks.
Step 3: Choose a phasing pattern
There is no single correct pattern. The right one depends on occupancy, the number of installers and how much noise the work creates. Common options are compared below.
| Pattern | How it works | Best suited to | Main drawback |
|---|---|---|---|
| Whole floor closed | One floor is taken out of sale and all doors are replaced together | Hotels with seasonal low periods or spare inventory | Loses the most room nights at once |
| Half floor or wing | Rooms on one side of a corridor are replaced, then the other | Mid-occupancy hotels with long corridors | Noise and dust reach neighbouring rooms |
| Room by room rolling | Rooms are released from housekeeping in small groups | Busy city hotels that cannot close floors | Longer total programme and more supervision |
| Mixed approach | Whole floors in quiet months, rolling work in busy periods | Hotels with clear seasonality | Needs careful forecasting with revenue management |
Whichever pattern you choose, agree it with the front office and revenue teams early. They know which rooms can be blocked and when.
Step 4: Plan production in batches that match the phases
Ordering every door in one shipment looks efficient, but it can leave you with hundreds of leaves stored in a corridor or basement. Splitting production into batches that match each phase reduces storage needs and handling damage.
When you discuss batches with Palmiye or any other manufacturer, agree these points in writing:
- Which rooms or floors are in each batch, and the delivery order.
- Whether the first batch is also the sample or mock-up approval batch.
- How leaves, frames and loose hardware will be labelled by room number.
- Who holds the finish reference, so later batches match the first one.
Lead time depends on the quantity, the finish, the approval process and the hardware, so it should be confirmed for your specific project rather than assumed.
Step 5: Approve a first-floor pilot
Before the programme runs at full speed, treat the first room or two as a pilot. Install a complete set of doors, including bathroom and wardrobe openings, and review fit, finish, hardware operation and the time each task actually takes.
The pilot gives you real installation durations for the programme, shows whether the survey was accurate, and lets the operator and designer sign off the look in a real corridor. Any correction is far cheaper at this stage than after several floors have been completed.
Step 6: Control delivery, storage and vertical movement
Getting doors into an operating hotel is often harder than making them. Plan the route from the loading point to each floor.
- Check service lift dimensions and weight limits against packed leaf sizes.
- Agree delivery windows outside check-in and check-out peaks.
- Use a dedicated storage room close to the working floor, kept dry and lockable.
- Protect corridor floors and walls on the delivery route.
- Keep leaves in their protective packing until the moment of installation.
For export projects, agree shipping terms such as FOB or DAP early, and think about how containers are unloaded and sequenced. Packing by phase means the first floor's doors can be unpacked without moving the rest.
Step 7: Minimise guest disruption on site
Guests notice noise, dust and smell more than they notice a new door. A few site rules go a long way.
- Limit noisy work such as frame removal and routing to agreed hours, usually mid-morning to mid-afternoon.
- Pre-finish doors in the factory so little painting or lacquering is needed on site, and fumes are avoided.
- Use dust sheets and temporary screens at the opening, and clean the corridor at the end of every shift.
- Fit a temporary lockable panel or leave the existing door in place until the new one is ready, so rooms are never left unsecured.
- Keep a clear contact person for the front desk to call if a room is needed urgently.
Where noise limits are strict, consider doing the demolition and frame work on empty floors first and leaving leaf hanging, which is quieter, for the occupied areas.
Step 8: Coordinate hardware, locks and fire requirements
Renovation doors often need to work with existing systems. Confirm the lock supplier, door contact and closer requirements before leaves are made, so routing and drilling are done in the factory. Check fire-rating and smoke-control requirements for corridor and room entrance doors with your local authority and consultant, because these affect which leaves, frames and seals can be used and how the paperwork must be presented.
Step 9: Sign off each room and each phase
Use a simple handover sheet per room: door operation, gaps, finish condition, hardware function and cleanliness. Housekeeping and engineering should both confirm before a room goes back on sale. Recording defects room by room gives you a clean punch list and a clear basis for any rework with the supplier.
Common mistakes to avoid
- Ordering all doors before surveying, then discovering that openings differ.
- Delivering faster than the site team can install, which fills corridors and causes damage.
- Leaving finish approval until late, so later batches do not match the first.
- Ignoring spare leaves and touch-up materials for the first year of operation.
Next step
If you are planning a phased renovation, send us your door schedule, survey notes or drawings, together with your preferred phasing pattern. We will review the openings and come back with a batch plan, suggested packing by floor and an estimated lead time for your project.
Sıkça Sorulan Sorular
Can doors be replaced while a hotel is still open?
Yes, many hotels do it by closing a floor, a wing or small groups of rooms at a time. Success depends on a prior survey, pre-finished doors, agreed working hours and a clear sign-off process before each room returns to sale.
How long does it take to replace a door in an occupied hotel room?
It depends on whether the frame is kept, the door type and the hardware. Pilot rooms give the most reliable figure, so time the first installations on your own site before building the full programme around any estimate.
Should I keep the existing door frames?
Keeping sound frames reduces noise, dust and installation time, but new leaves must then fit the existing openings accurately. A full survey shows whether frames are square and sturdy enough, or whether replacing them is the better choice.
How should doors be delivered to an operating hotel?
Deliver in batches that match each phase, packed and labelled by room number. Agree delivery windows outside peak hours, check service lift sizes and store leaves in a dry, lockable room near the working floor.
Do I need a mock-up room for a renovation?
A pilot room is strongly recommended. It confirms fit, finish and hardware, gives real installation times and lets the owner, operator and designer approve the look before the remaining batches are produced.
Every hotel project is different. Send us your drawings or room schedule for a tailored proposal on materials, lead time and shipping.